CIRCUMSTANCES OF CLAIMED VIOLATION

RESULTING IN A WRIT OF MANDAMUS

Report To

Mayor Sheldon Meyer and the Dunes City Council 

Prepared by Ralph Farnsworth and John Stead

 September 13, 2007

OVERVIEW

On August 9, 2007 , the City received a Petition for Alternative Writ of Mandamus (Writ) as prepared by Michael E, Farthing, Attorney for the Plaintiff (developer of Little Woahink). The petition seeks to compel City approval of what they refer to as; “The Woods at Little Woahink Subdivision Tentative Plan”, [i] and the “alternative subdivision application,” regarding Little Woahink PUD (01-06) and Little Woahink Phase III, which was hand delivered on March 2, 2007. [ii]    

The writ asserts that the 120-day time limit [iii] had expired without a decision so the City should be required to honor the request. [iv] At a special meeting of the City Council on August 28, the council appointed Ralph Farnsworth and John Stead, under the guidance of the City Attorney, to determine the facts regarding the 120-day time limit and give a report at the September 13th Council Meeting. [v] 

 The authors consulted with City Attorney Darnielle who suggested that we talk with Teri Tinker, review the records, describe the existing application process, and make recommendations on how the process might be strengthened.

 The applications’ paper trails, related statutes and City ordinances were reviewed. Findings were made, conclusions were drawn and recommendations were prepared.

 FINDINGS

1. Timing The Application Process: ORS 227.178 requires that final action including resolution of all appeals be taken 120 days after the application is deemed complete. [vi] The application is deemed complete upon a determination that the application complies with all applicable standards and criteria, [vii] including Comprehensive Plan and ordinance provisions. [viii] The Comprehensive Plan requires that final action occur 120 days after a complete application has been received, [ix] and under the “Old” City Code, the Planning Commission must consider the application no more than 45 days after submittal [x] and City Council consideration must take place no more than 45 days after Planning Commission action. [xi] Regarding PUD action by the Commission, the City Recorder shall notify the applicant in writing within five days. [xii]

2. Naming Applications: The Little Woahink subject property is commonly identified as Assessor’s Map 19-12-11-4, Tax Lot 100.  Names associated with this property have included: Little Woahink Lake Estates, [xiii]  Little Woahink Lake, [xiv] Little Woahink PUD, [xv] The Woods at Little Woahink PUD, [xvi] Little Woahink Phase III [xvii] (As recommended by LCOG’s Associate Planner [xviii]) Woods at Little Woahink Lake, [xix] Little Woahink Lake PUD, [xx] and, Little Woahink Lake PUD and Subdivision. [xxi]

3. The Application Process: The application process began in April, 2005 with the receipt of an application for Little Woahink Lake PUD. This application was accepted as complete on October 25, 2005. [xxii] *  Those who attended the Planning Commission meeting on September 15th learned that, “. . . the hearing on Little Woahink PUD had been postponed and would be heard October 20, 2005, but that anyone who would not be able to attend that meeting would be allowed to give testimony tonight since there was no open hearing.”[xxiii] The Planning Commission then took testimony from seven individuals. [xxiv]  The proposed October hearing was rescheduled to January, [xxv] and postponed to at least the February Planning Commission meeting. [xxvi]

 City Ordinance §155.048. (A), requires that the Planning Commission consider the application no more than 45 days after submittal, unless further information is required. [xxvii] At the March 2006 City Council meeting, the application for Little Woahink PUD was formally withdrawn. The City Attorney, “. . . said that the current application was not feasible and would have had to have been changed [and] . . . that the current application had to be completed within 240 days.”[xxviii]  LCOG’s Associate Planner advised the applicant that the 245 day window expired on April 28, 2006 .[xxix]

 The City received seven complete copies of, “Applications for Approval of Subdivision, Planned Unit Development and Zone Change (Little Woahink PUD)” on April 20, 2006. [xxx] On May 18th, the applicant was notified that additional information was needed. [xxxi]  On June 20th the application materials were provided and the City was informed simultaneously that the name had been changed to, “The Woods at Little Woahink PUD”. [xxxii]

 The application forms state that all information must be provided at least 30 days prior to the Planning Commission hearing. [xxxiii]  Eight copies of a Geotechnical Assessment were sent to the Planning Secretary on August 2nd, [xxxiv] and on August 23rd, as a follow up to telephone conversations, the Planning Secretary, as required by statute, [xxxv] sent a letter to the applicant requesting clarification of the issues. [xxxvi]

 * NOTE: See Eratta on Page 13.

At the December 28, 2006, Planning Commission Meeting, commissioners were assured that a waiver the statutory deadline had been submitted. [xxxvii] 

4. Alternative Subdivision Application:  On March 2, 2007, a letter delivered to the City Council % Joanne Hickey, City Recorder included new maps and reports. [xxxviii] This was followed on March 7th by a hand delivered letter containing additional documents.” [xxxix]

According to the Writ of Mandamus, the alternative subdivision application was submitted and accepted by the City on March 2, 2007. The applicant deemed it complete on March 2nd, [xl]  or no later than April 2nd. [xli]

The City’s new Ordinance 182 — Chapter 155 Zoning and Development — became effective December 25, 2006 . [xlii] 

As such, the City is required to immediately determine whether the application is complete. If the City is unable to deem the application complete, it shall not be accepted and shall be immediately returned to the applicant. [xliii]

No evidence was found to indicate that the City had taken the required action.  

5. The Writ filed in Circuit Court of the State of Oregon for Lane County on August 7, 2007 indicates that MLK,LLC, is an Oregon limited liability company.  [xliv]

According to the Oregon Business Registry this company was not renewed in June of 2007. Action taken was Administrative Dissolution. [xlv]  

6, The applicant(s) repeatedly added material after agreeing the application was complete. (So did the City.)  

CONCLUSIONS

See #1 – Compliance with the 120-day requirement calls for careful planning and procedures to be sure the City follows the law. In this case Staff and the City Attorney failed to insure that the City adhered to their own procedures.

 

See #2 – The name changes in the various applications for this parcel of land made communication difficult and created confusion for staff.

 

See #3 – The application processing procedures were not followed.

See #4 - The City failed to process this application as required by the City Code.

 

See #5 – The filing of the Writ is questionable.

 

See #6 – Once the application is deemed complete the file should not be left open as was done here repeatedly. This encouraged more confusion, made it difficult for citizen participation, and made it hard for Staff to do their job,

 

 

RECOMMENDATIONS

1. Following a determination of application status, (deemed complete or incomplete) the Planning Commission’s decision should immediately be conveyed to the applicant, in writing.

 2. Once an application is deemed complete the file is closed. No additions, deletions  nor changes are allowed unless the file is re-opened, reviewed, deemed complete again, after which the 120-day clock is re-started.

 

3. Once an application is filed with the City the name associated with the application should not be changed.

 

4. To facilitate application processing a ‘timeline based’ list of procedures, checklists, Flow Charts and  Control Charts should be developed to facilitate the application processing and status reporting as required by the statutes, the City’s Comprehensive Plan, and the City ordinances.

 

Control Charts should be maintained as the topmost sheet in the correspondence file so that the various dates are foremost in the Planning Secretary’s focus.

 5. To help the processing stay on track the City should consider splitting their files on any future development into two, and maintained as follows:  

a) A correspondence file containing the application and any letters regarding the flow of the process, to or from the applicant or any other interested parties.  

b) Any drawings or other materials of any kind either submitted or requested by the City should be put into an Engineering or Compliance file.

6. Applications should be reviewed when submitted and a list made of anything the City requires that hasn’t been provided. This list should be double checked by a designated member of the Planning Commission. 

7. Consider creating an Evidentiary Hearing and  Waiver Document such as is used by Portland . (See the attached copy of Portland’s Form and the Application Procedures sample from The Dalles.)  

    8.  Consider adding Application Procedures to Ordinance 182/155. (See the attached copy of Portland ’s Form and the Application Procedures sample from The Dalles.)

 

END NOTES


[i] Exhibit A, Date 02-27-07; Plat Date  Aug. 09, 2007;  Petition For Alternative Writ of   Mandamus, Kronberger vs. City of Dunes City, No. 16-07-01728,  Michael E. Farthing, Attorney at Law, August 9, 2007.

[ii] Letter dated March 2, 2007, Hand Delivered, from Michael Farthing to Dunes City Council,

% Joanne Hickey, City Recorder

   Re: Little Woahink PUD (01-06)

   Little Woahink Phase III

   The above matter is scheduled for public hearing on March 8. For your review and consideration at the public hearing,,(sic) I am enclosing several new maps and reports that respond to    issues and concerns that have been raised previously by staff, the Planning Commission, interested parties and individual Councilors. Fifteen (15) copies of each are provided. . .

[iii] ORS 227.178 specifies that final action is required within 120 days after the application is deemed complete—including resolution of all appeals.

[iv] Petition For Alternative Writ of Mandamus, Kronberger vs. City of Dunes City, 

   No. 16-07-01728, Michael E. Farthing, Attorney at Law, August 9, 2007.

[v] Mandamus Motion, Adopted at the Special Dunes City Council Meeting, August 28, 2007:

In view of the City’s rulings on the Little Woahink development applications and its related efforts to consider the public interests, which are jeopardized    by the filing of the writ of mandamus, I move for the following:  

   1)  that the City determine the nature of the  representations made by the Developer’s attorneys or other representatives to the City attorney or the City regarding any extension of the 120-day time limit and  

   2)  that the City appoint John Stead and Ralph  Farnsworth to act on behalf of  the City to work  under the guidance of the City attorney’s office  to determine the facts about extensions of this 120-day time limit and give a report at the        

 September Council Meeting.

[vi] ORS 227.178 Final action on certain applications required within 120 days; procedure; exceptions; refund of fees. (1) Except as provided in subsections (3) and (5) of this section, the governing body of a city or its designee shall take final action on an application for a permit, limited land use decision or zone change, including resolution of all appeals under ORS 227.180, within 120 days after the application is deemed complete.

[vii] ORS 227.180 (2) If an application for a permit, limited land use decision or zone change is incomplete, the governing body or its designee shall notify the applicant in writing of exactly what information is missing within 30 days of receipt of the application and allow the applicant to submit the missing information. The application shall be deemed complete for the purpose of subsection (1) of this section upon receipt by the governing body or its designee of:

   (a) All of the missing information;

   (b) Some of the missing information and written notice from the applicant that no other  information will be provided; or

  (c) Written notice from the applicant that none of the missing information will be provided.

(3)(a) If the application was complete when first submitted or the applicant submits the requested    additional information within 180 days of the date the application was first submitted and the city has a comprehensive plan and land use regulations acknowledged under ORS 197.251, approval or denial of the application shall be based upon the standards and criteria that were applicable at the time the    application was first submitted.

[viii] ORS 227.175 (4) The application shall not be approved unless the proposed development of land would be in compliance with the comprehensive plan for the city and other applicable land use regulation or ordinance provisions. The approval may include such conditions as are authorized by ORS 227.215 or any city legislation.

[ix] Comp Plan policy A16 – Final action shall occur 120 days after a complete application has been received by the City, as per ORS 227.178.

[x] DCC §155.048 . (A) The Planning Commission shall consider the tentative plan application and all reports and recommendations at a regular meeting no more than 45 full days after submittal of the tentative   plan. The Commission shall recommend approval, denial, or when further information is required, the    Commission may postpone a decision on the application.

(B) Approval must include affirmative findings that: (1) the tentative plan complies with all applicable provisions of state law requirements and city plans and policies and ordinances.

   [NOTE: This ordinance applies to those applications submitted prior to December 25, 2006.]

[xi] DCC §155.049 Review by the Council

The City Council shall consider the tentative plan application, the recommendations of the Planning Commission, and all reports at a regular meeting no more than 45 days after action by the Planning Commission. The Council shall approve, deny or, when further information is required, postpone a  decision on the application. Approval must include the affirmative findings listed in 155.048.

   [NOTE: This ordinance applies to those applications submitted prior to December 25, 2006.]

[xii]  DCC §156.185 [PUD Procedure For Preliminary Plan Approval]

(B) (3) Within five days following consideration by the Planning Commission of  the zone change   and accompanying preliminary development plan, the applicant shall be notified in writing by the City Recorder of the Commission’s action.

(4) The City Recorder shall forward approved Preliminary Planned Unit Development applications to the City Council for public hearing.

   [NOTE: This ordinance applies to those applications submitted prior to December 25, 2006.]

[xiii] Notice of Public Hearing, Siuslaw News, published September 7 and October 6, 2005

[xiv] Agenda, Planning Commission, Regular Meeting, September 15, 2005

[xv] Minutes, Planning Commission, Regular Meeting, September 15, 2005, (Page 1)

[xvi] Letter dated June 20, 2006, from Farthing to Dunes City Planning Commission,

    % Teri Tinker,

Re: The Woods at Little Woahink PUD (Formerly known as Little Woahink PUD)

[xvii] Letter dated October 25, 2006, from Michael Farthing to the Planning Commission,

Re: The Woods at Little Woahink PUD 01-06,

 Little Woahink Phase III

 [xviii] E-Mail   From: Dearborn, Hilary, 

   Sent: Wednesday, December 20, 2006 

   To: Teri Tinker

   Cc: Farthing, Michael

   Subject: RE: Little Woahink PUD

 I forgot to mention that I added a paragraph in the staff report to address the naming issue that    we've talked about. . . we can't have duplication of names, names that are too similar. Which is why "Little Woahink Phase III" is preferred. As required by Dunes City code.

 Hilary Dearborn

Associate Planner

       LCOG-Lane Council of Governments  

[xix] Supplemental Findings, Received December 13, 2006

[xx] Letter dated May 3, 2007, Hand Delivered from Michael Farthing to Mayor Meyer andDunes City Council,  % Joanne Hickey,

[xxi] Letter dated June 25, 2007, from Michael Farthing to Mayor Meyer and Dunes City Council,

[xxii]  Staff Report, Report date: November 14, 2006*

 Application Received:    April , 2005

Complete for Processing: October 25, 2006

Notice Published: November 15, 2006

Report Date:  November 14, 2006

Planning Commission

Hearing Date:November 21, 2005

[xxiii] Minutes, September 15, 2005, Planning Commission Regular Meeting (Page 1)

[xxiv] Minutes, December 15, 2005, Planning Commission, Regular Meeting (Pages 1 – 3)

[xxv] Minutes, December 15, 2005, Planning Commission Regular Meeting (Page 1)

[xxvi] Minutes, January 12, 2006, City Council (Page 2)

[xxvii] DCC §155.048 . (A)

   The Planning Commission shall consider the tentative plan application and all reports and recommendations at a regular meeting no more than 45 full days after submittal of the tentative plan. The Commission shall recommend approval, denial, or when further information is required, the  Commission may postpone a decision on the application.

  [NOTE: This ordinance applies to those applications submitted prior to December 25, 2006.]

[xxviii] Minutes, March 9, 2006, City Council (Page 37)

[xxix] E-Mail

  From: DEARBORN Hilary  

* NOTE: See Eratta on Page 13.

  Sent: Thursday, January 05, 2006 8:01 AM

  To: 'Martinlegal (at) cs.com'

  Cc: teridunescity (at) charterinternet.com; DARNIELLE Gary L; Christina (at) charterinternet.com

  Subject: RE: Developments--Little Woahink PUD

Regarding the Little Woahink PUD: Michael Farthing's letter of November 15, 2005 was the official request to postpone the hearing until January. . . I spoke to Mr. Farthing on Tuesday this week. . .

I advised Michael that the application must be processed within the 245 day window which expires    on April 28, 2006 , and that it would be best to hold the first public hearing at the February Planning   Commission meeting.

[xxx] Letter dated April 20, 2006, Hand Delivered, from Michael Farthing to Dunes City Council,  % Teri Tinker, Planning Secretary;

   Re: Applications for Approval of Subdivision, Planned Unit Development and Zone

Change (Little Woahink PUD)

Applicant: MJK, LLC

 Enclosed are seven complete copies of applications for subdivisions, planned unit development and zone change that I am submitting on behalf of MJK, LLC and its principal members, Darren and Alsia Kronberer. Also enclosed are separate checks for $1,000 (zone change) and $2,850 (subdivision and PUD) which I understand are the fees for these applications.

The applications include a lengthy narrative and several maps.

 [xxxi] Letter dated May 18, 2006, from Teri Tinker, Planning Secretary to MJK, LLC, Darren and    Alisa Kronberger, Copy to Michael Farthing.

[xxxii] Letter with enclosures dated June 20, 2006, from Michael Farthing to Dunes City Planning    Commission, % Teri Tinker

[xxxiii] Application for Considering a Proposal, dated April 20, 2006, received June 22, 2006, 

   from Michael Farthing, [The following information is found below the signature line on page 4 at the end of the application.]

   NOTE: All of the above information must be in the City Recorder’s office   at least THIRTY (30) DAYS PRIOR TO THE PLANNING COMMISSION HEARING  or your request will not be heard. . .

 IF THE PLANNING COMMISSION RECOMMENDS DENIAL, TO THE  CITY COUNCIL, THE APPLICANT MUST WITHIN 30 DAYS NOTIFY    THE CITY RECORDER THAT (1) THE APPLICANT WISHES THE   MATTER REVIEWED BY THE CITY COUNCIL AND DECIDED AS SUBMITTED, OR (2) APPLICANT WILL MODIFY THE APPLICATION TO THE PLANNING COMMISSION. 

[xxxiv] Letter dated August 2, 2006, from Michael Farthing to Teri Tinker

[xxxv] ORS 227.178

     (2) If an application for a permit, limited land use decision or zone change is incomplete, the governing   body or its designee shall notify the applicant in writing of exactly what information is missing within 30 days of receipt of the application and allow the applicant to submit the missing information.

[xxxvi] Letter dated August 23, 2006, from Teri Tinker, Planning Secretary, to Michael Farthing  Re: The Woods at Little Woahink PUD 01-06 Little Woahink Phase III

[xxxvii] Minutes, December 28, 2006, Planning Commission, Regular Meeting (Page 5)  Farthing said he did submit a waiver for the statutory deadline in which Dunes City must make a final decision (Exhibit B).

[xxxviii] Letter, dated March 2, 2007, Hand Delivered, from Michael Farthing to Dunes City Council,  % Joanne Hickey, City Recorder Re: Little Woahink PUD (01-06)  Little Woahink Phase III.

The above matter is scheduled for public hearing on March 8. For your review and consideration at the public hearing I am enclosing several new maps and reports that respond to issues and concerns that have been raised previously by staff, the Planning Commission, interested parties and individual Councilors. Fifteen (15) copies of each are provided.  

[xxxix] Letter, dated March 7, 2007, Hand Delivered, from Michael Farthing to Dunes City Council, c/o Joanne Hickey,    Re:The Woods at Little Woahink PUD      PUD 01-06, ZON 01-06                       

   As a further supplement to our application, I am enclosing two documents. . . Because of time constraints, we are only enclosing 12 copies of this document. . . We enclose 15copies of this letter for your review and inclusion in the record. . .We look forward to the hearing tomorrow night . .  

[xl] Petition For Alternative Writ of Mandamus, Kronberger vs. City of Dunes City, 

   No. 16-07-01728, Michael E. Farthing, Attorney at Law, August 9, 2007,

   (Pages 3 and 4)  

No additional information has been requested by the City to make application “complete” for processing in the meaning of ORS 227.178(2). Therefore, the application was deemed complete for processing on no later than March 2, 2007.  

[xli] Petition For Alternative Writ of Mandamus, Kronberger vs. City of Dunes City, 

   No. 16-07-01728, Michael E. Farthing, Attorney at Law, August 9, 2007, (Page 5)

. . . In the alternative, it was complete for processing by the passage of 30 days time on April 2, 2007.  

[xlii] Ordinance No.182 was adopted on December 12, 2006 — The new Chapter 155 Zoning

   and Development replaces the old Ordinances 155 and 156 — took effect on the thirteenth day after its enactment per the City Charter Section 35.  

[xliii] Chapter 155 Zoning and Development  

   155.4 — Application and Review Procedures  

  155.4.1.3 General Provisions

 A. 120-day Rule.

 The City shall take final action on Type III applications that are subject to this    Chapter within 120 days from the date the application is deemed complete. Any exceptions to this rule shall conform to the provisions of ORS 227.178. (The 120-day rule does not apply to Type IV legislative decisions – plan and code amendments – under    ORS 227.178.)                                   

 E. 2. a.  When the City receives an application, the Planning Secretary shall immediately determine whether the following essential items are present. If the following items are not present, the application shall not be accepted and shall be immediately returned to the    applicant;

 E. 3. e. If a new application is submitted by the applicant, that applicant shall be subject to a separate check for acceptance and completeness and will be subject to the standards and criteria in effect at the time the new application is accepted.

 [xliv] Petition For Alternative Writ of Mandamus, Kronberger vs. City of Dunes City,

No. 16-07-01728, Michael E. Farthing, Attorney at Law, August 9, 2007, (Page 1)

[xlv] Oregon Business Registry Business Name Search, dated September 13, 2007 (Page 2)

____________________________________________________________________________________

 ERATTA

 

CIRCUMSTANCES OF CLAIMED VIOLATION

RESULTING IN A WRIT OF MANDAMUS

Report To

Mayor Sheldon Meyer and the Dunes City Council

Prepared by

Ralph Farnsworth and John Stead

September 13, 2007

 

As the result of scrivener’s errors, please make changes as indicated in italics.  

Page 2

 11th line from the top begins:

     as complete on August 26, 2005 .

 Page 9

  XXII  Staff Report date: September 8, 2005

 Application Received:    July 21, 2005

Accepted as Complete:   August 26, 2005

Notice Published:September 8, 2005

Report Date: September 8, 2005 

Planning Commission

Hearing Date: September 15, 2005

XXIV Minutes, September 15, 2005

XXV Minutes, December 15, 2005, Planning Commission Regular Meeting (Page 3)

 We are sorry for the inconvenience.

RF and JS

###